Work on the Town’s 2013/2014 Roadway Construction contract was completed this summer by the Town’s contractor P.J. Albert, Inc. The roads resurfaced through this contract were “A” Street, Colonial Road, Gilbert Way, Hampton Street, Idle-wood Drive, Little Drive, Maria Avenue, Mill Street, Millbury Street, Sword Street, and West Street.

The Town’s Engineering Division is currently preparing the next contract for the 2015 construction season. The following roadways have been chosen for the upcoming contract:
Street

Bay Ridge Rd Ravine Dr. to Alpine Trail
Brook Road Rockland Rd to end
Burnett Street Rochdale St to Worcester City Line
Curtis Street Upland St to No. 33 Curtis St
Federal Hill Road Old Meeting House Rd to Condo Complex
George Street Stone St to South St
Goulding Drive Midstate Dr to end
Grove Street Stone St to end
Heritage Drive Old Meetinghouse Rd to Appleton Rd
Hickory Lane Arrowhead Ave to Saratoga Rd
Highland Street Auburn St to Pearl St
Jefferson Drive Mt View Ave to end
Karen Avenue Burnett St to Lorna Dr
Lorna Drive Rochdale St to John William Dr
Mount View Ave Arrowhead Ave to end
Munger Drive Arrowhead Ave to end
Ravine Drive Shore Dr to Alpine Trail
Sara Drive Lorna Dr to Lorna Dr
Shore Drive Woodland Rd to No. 50 Shore Dr
Stone Street Elm St to South St
Westlund Ave Harrison Ave to Westlund Ave Extension
Wethered Street Highland St to Rockland Rd